Earned Value calculators
PV, EV, AC, variances, CPI, SPI and every documented EAC model.
Calculate Planned Value step by step: PV = BAC × planned % complete at the status date.
Calculate Earned Value step by step: EV = BAC × actual % complete.
Calculate Actual Cost (Earned Value) step by step: AC = sum of all costs actually incurred for the work performed to the status date.
Calculate Budget At Completion step by step: BAC = sum of the budgets of all work packages in the performance measurement baseline.
Calculate Cost Variance step by step: CV = EV − AC.
Calculate Schedule Variance step by step: SV = EV − PV.
Calculate CPI step by step: CPI = EV ÷ AC.
Calculate SPI step by step: SPI = EV ÷ PV.
Calculate EAC with four documented models: BAC ÷ CPI, AC + (BAC − EV), AC + (BAC − EV) ÷ (CPI × SPI), and AC + bottom-up ETC.
Calculate ETC step by step: ETC = EAC − AC; or (BAC − EV) ÷ CPI; or BAC − EV at the budgeted rate.
Calculate VAC step by step: VAC = BAC − EAC.
Calculate TCPI step by step: TCPI (BAC) = (BAC − EV) ÷ (BAC − AC).
Calculate Percent Complete step by step: Percent complete = EV ÷ BAC (or units done ÷ total units).