Skip to content

Schedule Performance Index (SPI) Calculator

Measure how much of the planned work the project has actually completed.

Amounts are shown in the currency you pick. No exchange rate is applied.

Earned value (EV) is required.

Planned value (PV) is required.

Press Calculate, or Enter in any field.

$80,000 earned against $100,000 planned

An SPI of 0.8 — one fifth of the planned work is outstanding.

Complete the required fields to see the result.

What this calculator does

Earned value divided by planned value; the schedule variance is the difference between them. Both values come from the project's measurement baseline.

Inputs and what they mean

Currency
Amounts are shown in the currency you pick. No exchange rate is applied..
Earned value (EV)
number value.
Planned value (PV)
number value.

How to use it

  1. Enter your own figures — the calculator never fills in a rate, price or benchmark for you.
  2. Press Calculate to see the result.
  3. Read the formula, variables, assumptions and source below the result before you rely on it.

Formula

SPI = EV ÷ PV; SV = EV − PV

Worked example

$80,000 earned against $100,000 planned

An SPI of 0.8 — one fifth of the planned work is outstanding.

Reading the result

The headline figure is the main answer. Any breakdown underneath shows the parts that make it up, so you can check the working and see what changes when you adjust an input.

Limitations and assumptions

Results depend entirely on the figures you enter and are rounded for display. They are for general information and education, not professional advice.

Reference: PMI — Earned value management — PMI practice guidance

Last reviewed:

Common questions

Formula, source and verification

Earned value divided by planned value; the schedule variance is the difference between them.

The question it answers: Have we completed as much work as we planned to by now?

The formula

SPI = EV ÷ PV; SV = EV − PV

EVEarned value
(currency). Budgeted cost of completed work.
PVPlanned value
(currency). Budgeted cost of work scheduled to date.

Units: Currency in; dimensionless index and currency variance out.

What kind of calculation this is

Deterministic formula. The same inputs always give the same answer. The maths is fixed and does not depend on judgement.

Method

Both values come from the project's measurement baseline.

Assumptions built into the result

  • Operational: Earned value and planned value are measured to the same date.

Figures this calculator will never guess for you

  • No assumed schedule buffer or productivity factor.

Limitations

  • Near the end of a project SPI tends towards 1 even when the project is late; use schedule analysis as well.

Source and version

Standard or reference
Earned value management — PMI (PMI earned value management practice guidance: SPI and SV definitions.)
Published source
PMI — Practice guidance
Formula version
Version 1
Verification
Reviewed against the cited source on
How much weight the source carries
Standards or government
Applies to
Currency
Amounts stay in the currency you choose; no exchange rate is applied.

Related tools

Work out the hourly rate to charge a client so that target margin is met after overhead and non-billable time.

Professional & Industry

Find the true hourly cost of an employee once benefits, payroll cost and overhead are included.

Professional & Industry

Size a software application from its data and transaction functions before estimating effort or cost.

Professional & Industry

Estimate development effort, schedule and average team size for a software project of a known size.

Professional & Industry

Express cloud spend as a cost per customer, per transaction or per other business unit.

Professional & Industry

Set the rate used to apply manufacturing overhead to jobs for the coming period.

Professional & Industry